Firefly Fiber Broadband updated its project chart on September 28, 2026. It lists four Cumberland County areas as finished and four that are still being hooked up: Clinton, Gravel Hill, Hatchers and Lawford/Hatcher. If you live in one of those four, timing matters. Firefly waives its $100 installation fee for anyone who registers while crews are still working the area. No calendar date ends that waiver. It ends when the area's status changes, and the status changes after the homes already registered there are connected.
So the deadline for a free install on your road depends on how many of your neighbors signed up before you. Here is how the pieces fit together, starting with where each area stands.
Where Each Firefly Area Stands as of September 28
Firefly is the broadband company owned by Central Virginia Electric Cooperative. In Cumberland, it reports progress by project area, not by road or address. On the September 28 chart, the Cumberland list reads like this:
| Project area | Status on Firefly's Sept. 28, 2026 chart |
|---|---|
| CARES – Cumberland | In-Service |
| ReConnect – Cumberland | In-Service |
| RISE Cartersville Extension | In-Service |
| RISE Trents Mill Rd | In-Service |
| RISE Clinton | Connecting Now |
| RISE Gravel Hill | Connecting Now |
| RISE Hatchers | Connecting Now |
| RISE Lawford/Hatcher | Connecting Now |
Firefly's Cumberland County page also lists two more areas as In-Service: CVEC – Ampthill and CVEC – Cartersville. That page was last updated in May 2026, so the September chart is the newer of the two. On the RISE areas, the page and the chart agree.
None of this is new for Cartersville or the Trents Mill Road corridor. The four areas still in progress are where the real news is.
What Actually Moves an Area to In-Service
Firefly defines its two final stages plainly:
"Connecting Now" means that fiber construction is now complete and connections have begun in the service area. Service drops will continue until all pre-registered homes have service at which time the area will be considered "In-Service."
That definition has two practical effects for anyone in Clinton, Gravel Hill, Hatchers or Lawford/Hatcher.
First, the main fiber line is already in. In an area marked Connecting Now, the remaining work is the service drop, the line that runs from the road to an individual house.
Second, the stage ends when the queue runs out. Crews work through the homes that registered ahead of time, and once the last of those has service, the area becomes In-Service. Firefly's latest chart gives no completion date for the four Cumberland areas still connecting. No source gives a date for the switch either. It depends on how quickly crews finish the drops already on their list.
Delays have happened here before. In August 2023, the Farmville Herald reported a connection backlog lasting several months in Cumberland, partly because the contractors who mark underground utilities through 811 were behind. In December 2023, the Herald reported that hunters had damaged fiber lines, which pulled Firefly crews off new construction to make repairs. Neither report describes 2026 conditions. They do show that a connection queue in this county can move faster or slower than a project chart suggests.
The $100 Line in the Fine Print
On Firefly's Cumberland page, each area's note changes as the area moves through the stages. Areas at service-drop construction read: "Register now while crews are working in your area, and we will waive the $100 installation fee." Areas marked In-Service read: "Since construction work in your area is finished, the $100 installation fee now applies."
In Cartersville and along Trents Mill Road, that switch has already happened. A household there that orders now pays the installation fee. In the four RISE areas still connecting, registering avoids the fee for as long as crews remain in the area.
Here are the residential plans as posted on Firefly's rate page in May 2026. All are symmetrical, with no data caps and no contract:
- Firefly Light: 300 Mbps for $54.99 a month, or $49.99 with ACH AutoPay
- Firefly Flash: 1 Gbps for $84.99 a month, or $79.99 with ACH AutoPay
- Firefly Lightning: 2 Gbps for $104.99 a month, or $99.99 with ACH AutoPay, in select areas only
Firefly says taxes and fees may apply. It asks customers to contact the company about installation and equipment charges. That rate page is several months old, so confirm the current price before you sign up.
South of the Courthouse, It's a Different Company
Firefly's chart only answers the question for part of the county. Cumberland County lists two broadband partners: Firefly, and Kinex, which works through a partnership of Cumberland, Prince Edward and Lunenburg counties and the Commonwealth Regional Council.
The split goes back to 2022. The Farmville Herald reported that Firefly would cover the area from Route 60 north to the James River. Kinex's build ran from Cumberland Courthouse village south toward Farmville.
The county's own numbers show how close to even the split is. The county counts 4,416 total passings. State broadband grant applications use "passings" to mean the serviceable units in a project area. Firefly's RISE and CVEC projects account for 2,470 of them. Kinex accounts for 1,946, along 239 miles of fiber at about $8.5 million in construction costs. Those two figures add up exactly to the county total. That makes Kinex the provider for roughly 44 percent of the county's planned fiber passings, even though Firefly's chart is the one people tend to check.
Kinex also has a new owner. Its website now says Planet Networks acquired Kinex Telecom, and the embedded press release is dated February 7, 2025. Customers are directed to Planet Networks. Local help is still at the Farmville office, 717 E. 3rd St., at (434) 392-4804. Planet's residential page lists symmetrical plans at 250 Mbps, 500 Mbps, 1 Gbps, 2.5 Gbps and 5 Gbps. It does not show monthly prices, so get a quote for your address. The county's broadband sheet still shows an older Kinex rate table. That table is undated and does not reflect Planet's current lineup.
The county lists the Kinex timeline as "Completed Build Out 2026." At the Commonwealth Regional Council's December 17, 2025 meeting, staff reported 55 installations in the previous month and regular site visits to Planet Networks crews. That puts work still underway at the end of 2025. No newer public report confirms the Kinex build in Cumberland is finished.
Checking One Address
The project names cover areas, not every driveway in them. Even in an In-Service area, a given house may or may not be able to order. Firefly sends residents to its address checker for a definite answer. For a single house in Cumberland, a few steps settle it:
- Figure out which side of the split you're on. North of Route 60 toward the James is Firefly territory. Around and south of Cumberland Courthouse toward Farmville is Kinex territory, now Planet Networks.
- For Firefly, enter your address at register.fireflyva.com or call (833) 473-3591. If you're in Clinton, Gravel Hill, Hatchers or Lawford/Hatcher, registering now is what gets you the fee waiver.
- For Kinex areas, use Planet Networks' availability checker on planet.net or call the Farmville office. Ask about installation charges when you do. None of the published Kinex or Planet material lists a Cumberland installation fee.
- Don't count on the main line by the road to tell you anything. Dominion Energy's rural broadband program lists its Cumberland work as being in construction. That is middle-mile fiber, a separate stage from the last-mile connection to your house.
What the County Put In
The county's broadband update puts total broadband investment in Cumberland at about $15.8 million, across roughly 380 miles of fiber. The county's own share is $586,250, or 3.7 percent, paid from CARES and ARPA funds. Firefly's projects alone total $7,339,060. That includes a $5,759,320 project funded through VATI, the Virginia Telecommunications Initiative grant program, which covers 64 miles of fiber. The county approved a $386,250 match for that work. The Herald's December 2023 report described a contingent county contribution of $250,000. The two documents don't explain the difference, so the county's own figure is used here.
The same 2023 Herald report set the goal: 99 percent of Cumberland able to get fiber by the end of 2026. As of this fall, Firefly's construction is finished in every Cumberland area on its chart, and the four remaining areas are down to service drops. For a household in Clinton, Gravel Hill, Hatchers or Lawford/Hatcher, whether the install is free comes down to registering before crews finish the drops already on their list.
If you're weighing a Cumberland property and want to know which provider serves that road and whether fiber is actually at the house, Joey Wray checks that as part of every rural search and sale. Let's Connect.